What is a submittal log in construction?
By the DailyBuild team - Published - 5 min read

Short answer
A submittal log is the running register of every submittal on a project - shop drawings, product data, samples and certificates - showing what was sent, when, to whom, and the status of the review. It is the contractor's tool for proving materials were approved before they were bought or installed.
Key takeaways
- The log tracks submittals, not the submittals themselves; the documents live in the project files it points to.
- Every row ties back to a spec section, so the log doubles as a check that nothing in the specs was missed.
- Status and returned date are the two columns that matter most - they show what is blocking procurement.
- The general contractor usually owns the log; the architect or engineer owns the review.
- Late submittals are a schedule problem before they are a paperwork problem, so the log should be reviewed weekly.
On any job with a specification, materials cannot simply be ordered. They have to be submitted, reviewed and accepted first. A submittal log is the single list that keeps that process visible: what has been sent, what is still with the reviewer, what came back needing revision and what is cleared for purchase.
What a submittal log tracks
A useful log has one row per submittal and enough columns to answer, at a glance, whether a material is clear to buy. Most logs carry these fields.
| Column | What it records |
|---|---|
| Submittal number | Sequential ID, often tied to the spec section, such as 03 30 00-001 |
| Spec section | The specification section the submittal answers |
| Description | The item - concrete mix design, door hardware schedule, light fixture cut sheets |
| Type | Shop drawing, product data, sample, mock-up, certificate, O and M manual |
| Responsible subcontractor | Who produced the submittal |
| Date sent | When it went to the design team |
| Reviewer | Architect, engineer or consultant handling the review |
| Date due | Contract review period, commonly 14 calendar days |
| Date returned | When the reviewed submittal came back |
| Status | No exceptions taken, make corrections noted, revise and resubmit, rejected |
| Revision | Which submission this is - 0 for the original, 1 for the first resubmittal |
| Lead time | Fabrication and delivery time once approved, so the log connects to the schedule |
The submittal review cycle
The cycle is the same on most projects, whatever the software. The subcontractor prepares the submittal, the general contractor reviews and stamps it, the design team reviews and returns it with a status, and the contractor distributes the result. If the status requires changes, the submittal goes back around with a new revision number.

Typical review statuses
- No exceptions taken or approved - proceed with fabrication and purchase.
- Make corrections noted or approved as noted - proceed, incorporating the marked comments.
- Revise and resubmit - the item is not accepted yet; correct and submit again as a new revision.
- Rejected - the proposed item does not comply; submit something different.
- For information only or reviewed for record - no action required.
The exact wording of these statuses is set by the contract documents. Always use the language in your specification rather than assuming the standard set applies.
Sample submittal log
| No. | Spec section | Description | Sent | Returned | Status |
|---|---|---|---|---|---|
| 03 30 00-001 | 03 30 00 | Concrete mix designs | Mar 4 | Mar 15 | No exceptions taken |
| 05 12 00-001 | 05 12 00 | Structural steel shop drawings | Mar 6 | Mar 24 | Make corrections noted |
| 08 71 00-001 | 08 71 00 | Door hardware schedule | Mar 11 | Mar 26 | Revise and resubmit |
| 08 71 00-002 | 08 71 00 | Door hardware schedule rev 1 | Apr 2 | Pending | In review |
| 26 51 00-001 | 26 51 00 | Interior lighting cut sheets | Mar 18 | Pending | In review |
Who owns the submittal log?
The general contractor normally builds and maintains the log, because the contractor is responsible for delivering complete submittals and for the procurement schedule that depends on them. Subcontractors feed it, the architect or engineer of record performs the review, and the owner or construction manager reads it to see whether the job is on track. On a smaller project the superintendent or project manager keeps it directly.
Why the log matters more than it looks
Sort the log by date sent and anything past the contract review period is a conversation to have this week. Sort by lead time and you can see which pending approvals actually threaten the schedule. That is the difference between a log that is filled in and a log that is used.
Submittals and RFIs are not the same thing
A submittal proposes what will be installed and asks the design team to confirm it complies. An RFI asks a question about the documents when something is unclear, conflicting or missing. A rejected submittal often produces an RFI, and an RFI answer often triggers a resubmittal, but they are separate logs with separate numbering.
Frequently asked questions