What is a pour card in construction?
By the DailyBuild team - Published - 5 min read

Short answer
A pour card is the field record of one concrete placement. It captures where the concrete went, which mix design was used, how much was placed, the weather, the fresh concrete test results and the IDs of the test cylinders taken, all signed off by the inspector or superintendent.
Key takeaways
- One pour card equals one placement, not one day and not one truck.
- It links a physical location on the job to the mix design, tickets and cylinder breaks that prove it.
- Fresh concrete tests - slump, air content, temperature - are recorded on the card at the time of placement.
- Pour cards are usually required by the spec, the inspection agency or the building department, not optional paperwork.
- The pour card and the daily report should agree; the daily report is the narrative, the pour card is the technical record.
Concrete is one of the few things on a jobsite that cannot be inspected after the fact without destructive testing. Once it is placed and cured, the only evidence of what went in is the paperwork created while it was being placed. That paperwork is the pour card.
What a pour card records
Formats differ by contractor, inspection agency and jurisdiction, but the information is consistent. A pour card connects a location to a mix, a quantity, a set of test results and a set of samples.
| Field | What it captures |
|---|---|
| Pour number and date | Sequential ID for the placement and the date it happened |
| Location | Grid lines, level, element - for example slab on grade, bays A4 to C7 |
| Element type | Slab, footing, wall, column, deck, pier |
| Mix design number | The approved mix, tied back to the approved submittal |
| Specified strength | Design compressive strength and the age it is measured at, commonly 28 days |
| Quantity placed | Cubic yards from the delivery tickets, plus ticket numbers |
| Placement method | Chute, pump, bucket, conveyor |
| Start and finish times | First truck discharged, last truck discharged |
| Weather | Air temperature, wind, precipitation, and concrete temperature |
| Fresh concrete tests | Slump, air content, unit weight, concrete temperature |
| Cylinder or specimen IDs | The set identifiers and break schedule for lab testing |
| Reinforcement inspection | Confirmation that rebar was inspected and released before placement |
| Curing method | Wet cure, curing compound, blankets, hoarding |
| Sign-off | Superintendent, testing technician and inspector signatures |

When a pour card is required
Requirements come from the contract documents and the authority having jurisdiction, so always check the concrete specification section and the approved special inspection program for your project. In general, expect a pour card whenever any of the following applies.
- The concrete is structural and subject to special inspection.
- The spec requires field testing of fresh concrete and cylinder sampling.
- The building department requires inspection records for permit closeout.
- The owner requires a placement record as part of the quality program.
- Placement happens in hot or cold weather where temperature limits must be documented.
Fresh concrete tests on the card
The testing technician performs the tests; the pour card records them. Acceptance limits are set by the mix design and the specification, so the card exists to prove the concrete was within those limits when it was placed, not to define them.
| Test | What it measures | Why it is on the card |
|---|---|---|
| Slump | Workability and consistency of the mix | Detects water added on site outside the mix design |
| Air content | Entrained air percentage | Freeze-thaw durability depends on it |
| Concrete temperature | Temperature of the delivered concrete | Hot and cold weather placement limits |
| Unit weight | Density of the fresh concrete | Cross-check on yield and mix consistency |
| Cylinders cast | Number and IDs of specimens taken | Links the placement to the lab break results |
Cylinder break schedules vary by spec. A common arrangement is one set per placement or per a set volume of concrete, with breaks at 7 and 28 days plus a spare, but the number of specimens, sampling frequency and break ages are all defined by your specification and the referenced standards.
Pour card versus daily report
They serve different purposes and both should exist. The daily report says a pour happened, who was on site, what the weather was and how the day went. The pour card is the technical record for that one placement, with the mix, quantities and test data an inspector or a forensic engineer will want years later.
Practical tips for filling out pour cards
- Open the card before the first truck arrives, not at the end of the day.
- Staple or attach every delivery ticket; ticket numbers on the card make it auditable.
- Photograph the cylinder set with its ID labels visible.
- Note any water added on site and who authorised it - this is the field note that matters most in a dispute.
- Record who released the rebar inspection and when, so the sequence is provable.
- Close out the card with signatures the same day while everyone is still on site.
Frequently asked questions