    What is a pour card in construction?

    By the DailyBuild team - Published - 5 min read

    Line illustration of a concrete mixer truck beside concrete test cylinders

    Short answer

    A pour card is the field record of one concrete placement. It captures where the concrete went, which mix design was used, how much was placed, the weather, the fresh concrete test results and the IDs of the test cylinders taken, all signed off by the inspector or superintendent.

    Key takeaways

    • One pour card equals one placement, not one day and not one truck.
    • It links a physical location on the job to the mix design, tickets and cylinder breaks that prove it.
    • Fresh concrete tests - slump, air content, temperature - are recorded on the card at the time of placement.
    • Pour cards are usually required by the spec, the inspection agency or the building department, not optional paperwork.
    • The pour card and the daily report should agree; the daily report is the narrative, the pour card is the technical record.

    Concrete is one of the few things on a jobsite that cannot be inspected after the fact without destructive testing. Once it is placed and cured, the only evidence of what went in is the paperwork created while it was being placed. That paperwork is the pour card.

    What a pour card records

    Formats differ by contractor, inspection agency and jurisdiction, but the information is consistent. A pour card connects a location to a mix, a quantity, a set of test results and a set of samples.

    Typical pour card fields
    FieldWhat it captures
    Pour number and dateSequential ID for the placement and the date it happened
    LocationGrid lines, level, element - for example slab on grade, bays A4 to C7
    Element typeSlab, footing, wall, column, deck, pier
    Mix design numberThe approved mix, tied back to the approved submittal
    Specified strengthDesign compressive strength and the age it is measured at, commonly 28 days
    Quantity placedCubic yards from the delivery tickets, plus ticket numbers
    Placement methodChute, pump, bucket, conveyor
    Start and finish timesFirst truck discharged, last truck discharged
    WeatherAir temperature, wind, precipitation, and concrete temperature
    Fresh concrete testsSlump, air content, unit weight, concrete temperature
    Cylinder or specimen IDsThe set identifiers and break schedule for lab testing
    Reinforcement inspectionConfirmation that rebar was inspected and released before placement
    Curing methodWet cure, curing compound, blankets, hoarding
    Sign-offSuperintendent, testing technician and inspector signatures
    Diagram of pour card fields with a thermometer, form card and slump cone
    The pour card ties conditions, tests and samples to one placement.

    When a pour card is required

    Requirements come from the contract documents and the authority having jurisdiction, so always check the concrete specification section and the approved special inspection program for your project. In general, expect a pour card whenever any of the following applies.

    • The concrete is structural and subject to special inspection.
    • The spec requires field testing of fresh concrete and cylinder sampling.
    • The building department requires inspection records for permit closeout.
    • The owner requires a placement record as part of the quality program.
    • Placement happens in hot or cold weather where temperature limits must be documented.

    Fresh concrete tests on the card

    The testing technician performs the tests; the pour card records them. Acceptance limits are set by the mix design and the specification, so the card exists to prove the concrete was within those limits when it was placed, not to define them.

    Fresh concrete tests commonly recorded on a pour card
    TestWhat it measuresWhy it is on the card
    SlumpWorkability and consistency of the mixDetects water added on site outside the mix design
    Air contentEntrained air percentageFreeze-thaw durability depends on it
    Concrete temperatureTemperature of the delivered concreteHot and cold weather placement limits
    Unit weightDensity of the fresh concreteCross-check on yield and mix consistency
    Cylinders castNumber and IDs of specimens takenLinks the placement to the lab break results

    Cylinder break schedules vary by spec. A common arrangement is one set per placement or per a set volume of concrete, with breaks at 7 and 28 days plus a spare, but the number of specimens, sampling frequency and break ages are all defined by your specification and the referenced standards.

    Pour card versus daily report

    They serve different purposes and both should exist. The daily report says a pour happened, who was on site, what the weather was and how the day went. The pour card is the technical record for that one placement, with the mix, quantities and test data an inspector or a forensic engineer will want years later.

    Practical tips for filling out pour cards

    1. Open the card before the first truck arrives, not at the end of the day.
    2. Staple or attach every delivery ticket; ticket numbers on the card make it auditable.
    3. Photograph the cylinder set with its ID labels visible.
    4. Note any water added on site and who authorised it - this is the field note that matters most in a dispute.
    5. Record who released the rebar inspection and when, so the sequence is provable.
    6. Close out the card with signatures the same day while everyone is still on site.

    Frequently asked questions