    Free Weekly Construction Progress Report Template

    The weekly report an owner will actually read: planned against actual progress by area, open issues with schedule and cost exposure, a two-week look-ahead and the manpower and safety totals.

    Download Free Excel TemplateDownload Print-Ready PDF
    Create a daily report

    14-day free trial. No credit card required

    Preview Template
    • No signup required
    • Excel and Google Sheets
    • Print-ready PDF included
    • 100% free
    Free weekly construction progress report template preview showing the printable jobsite layout
    DailyBuild_Free_Weekly_Construction_Progress_Report_Template.xlsx
    Download
    Free bundle

    Get all 30 construction templates

    Editable Excel files plus the paper-to-app checklist. Enter your email for the complete construction bundle.

    Instant download | One email list | Unsubscribe anytime

    What's inside the template

    Built from records that hold up when somebody asks.

    Planned vs actual

    Percentage complete by area with the variance visible.

    Work completed

    One line per scope, written so a reader who was not on site understands it.

    Issues and delays

    Issue, owner, days of schedule impact, cost exposure and target close date.

    Two-week look-ahead

    Planned activities, crews and the constraints that must clear first.

    Manpower totals

    Man-hours and peak headcount for the week and project to date.

    Safety totals

    Toolbox talks, recordables, near misses and days lost to weather.

    What's included

    Two files, no signup, nothing locked.

    An .xlsx workbook you can edit and a formatted PDF you can print for the truck or the trailer wall.

    Excel workbook (.xlsx)

    Opens in Microsoft Excel, Numbers and Google Sheets. Edit every column and add your own.

    Print-ready PDF

    Landscape, fit to one page width, with sample rows you can clear before printing.

    Sample entries

    A few filled rows so the crew can see the level of detail expected, then blank rows to work in.

    Free to share

    Send it to your subs, your PM, or your whole company. No email address, no watermark.

    The short answer

    Weekly Construction Progress Report Template: what it is and how to fill it out.

    A weekly construction progress report summarises one week on a project: percentage complete planned against actual by area, work completed, open issues and delays with their schedule impact, the activities planned for the next two weeks, and weekly totals for man-hours and safety.

    Write it for the person who was not there

    The audience is an owner, a lender or an executive who sees the job once a month. Lead with the number that matters (are we on the contract date), then the exceptions. Detail belongs in the daily reports the weekly report draws from.

    Variance is the whole report

    Planned against actual is what makes a progress report a management tool instead of a newsletter. If Level 3 mechanical was planned at 45 percent and sits at 38, that gap with a named cause and an owner is the single most useful line on the page.

    The look-ahead is where delays get prevented

    Listing next week's activities with the constraint that must clear first (a crane window, an inspection sign-off, an owner-supplied item) turns the report into an action list. Constraints raised two weeks out get solved; the same constraint raised on the day becomes a delay.

    How to use it

    Four steps, start to finish.

    1. 1

      Pull the week's daily reports

      Work completed, hours, delays and safety events feed straight in.

    2. 2

      Fill planned against actual

      By area or scope, with a one-line comment on any gap.

    3. 3

      List issues with owners and dates

      Schedule impact in days, cost exposure and a target close date.

    4. 4

      Build the two-week look-ahead

      Activity, crew and the constraint that must clear, then send it Friday.

    Before and after

    What changes once the record is consistent.

    Without a set format

    • Owners hearing about slippage late
    • Progress described without numbers
    • Issues with no owner and no date
    • Constraints discovered on the day
    • Weekly totals rebuilt from scratch

    With this template

    • Variance visible every Friday
    • Issues owned and dated
    • A look-ahead that clears constraints early
    • Consistent weekly and cumulative totals
    • A report the owner reads in two minutes

    Excel vs. DailyBuild

    When the spreadsheet stops keeping up.

    The template is free and it works. When the same record has to be captured every day, by several people, from the field, an app does it faster.

    CapabilityExcel TemplateDailyBuild Software
    Planned vs actual by area
    Issue and delay register
    Two-week look-ahead
    Totals pulled from daily reports automatically
    Photos of the week's progress
    PDF sent to the owner on a schedule
    Trends across the whole project

    What changes when you switch

    • Weather fills itself in for every report
    • Crew hours flow straight into timesheets
    • One tap sends a branded, signed PDF
    Start Free Trial

    Ready to do this from your phone?

    Inside DailyBuild

    Daily reports in DailyBuild

    • Weather fills in automatically
    • Crew sign-off on every report
    • Branded PDF export in one tap
    Start Free Trial

    No credit card required to start your trial

    Frequently asked

    Weekly Construction Progress Report Template FAQs

    Free iPhone and Android apps

    Run these logs from your phone

    The DailyBuild app turns the same daily report, timesheet and punch list into something your crew fills out on site - photos, hours and signatures included, with branded PDFs sent automatically.

    Download DailyBuild on the App StoreGet DailyBuild on Google Play
    DailyBuild mobile app Today screen with today's report, time, photo and safety actions

    Send a progress report the owner trusts.

    Download the template free, or let DailyBuild capture the same record on your phone and email the PDF before you leave the jobsite.